Review Assessment Report
Part 1: Contact & Program Identification
Report Year and Contact Information | ||
---|---|---|
Academic Year | Modified By | Date Modified |
2022-2023 | [email protected] | 2023-10-19T20:37:18.204Z |
School | Name of Program | Courses |
---|---|---|
BIT | Project Management Certificate | BCIS 1110,BLAW 2110,BUSA 1198,BUSA 2195,BUSA 2198 |
Part 2: Program Summary
Provide a high level review of the program to include highlights, successes, challenges, significant changes, and significant resources needed to support the program |
---|
The Project Management Certificate of Completion provides opportunities for the business leaders and project managers of tomorrow to achieve a high-quality, high-value education that enables them to succeed in a competitive market. Emphasis is placed on hands-on experiences, conducting real-world research and community projects. |
Part 3: Data Review
2020-2021 | 2021-2022 | 2022-2023 | |
---|---|---|---|
Annual number of graduate awards is greater than 10 | 21 | 25 | 35 |
Number of declared majors | 43 | 39 | 42 |
Average Class Size | 21.3 | 19.3 | 19.1 |
Annual Average Class withdrawal rate is 30% or below (SAGE 35%) | 10% | 11% | 13% |
Annual C-Pass rate for coursework is 60% or above | 72% | 69% | 69% |
Average class fill rate at 60% or above capacity within a term or over a year | 73% | 69% | 69% |
Graduate Transfer to 4-year Schools | 10% | n/a | n/a |
Full-time Faculty Coverage by Section | 55% | 51% | 18% |
Summarize how your program met or did not meet the target measures based on the data above |
---|
Targets Met |
Part 4: Program Learning Outcome Analysis
Learning Outcome | Population or Course(s) Assessed | Description | Summary of Assessment Results |
---|---|---|---|
1. Demonstrate knowledge and skills in basic project management and organization (Not measured this cycle). | BUSA 1198
Final Project
|
| BUSA 1198: 64% of students met the goal of having 71% of students achieve 71% or higher on their final project
|
2. Evaluate systems and procedures for budgeting, cost control, and earned value in project management (Not measured in this cycle). | BUSA 1198
Final Project
|
| BUSA 1198: 64% of students met the goal of having 71% of students achieve 71% or higher on their final project
|
3. Interpret project documents, specifications, contracts, and subcontracts. | BUSA 2198
Final Project
|
| BUSA 2198: 69% of students met the goal of having 71% of students achieve 71% or higher on their final project
|
4. Develop a systematic approach to cost control and project scheduling techniques. | BUSA 1198
Final Project
|
| BUSA 1198: 64% of students met the goal of having 71% of students achieve 71% or higher on their final project
|
5. Illustrate proficiency in the use of computers and project management related software including managing, budgeting, project scheduling and basic word processing. | BUSA 2198
Final Project |
| BUSA 2198: 69% of students met the goal of having 71% of students achieve 71% or higher on their final project
|
Interpretation of Assessment findings |
---|
These classes (and projects) have been taught using the Pathstream LMS which has resulted in targets being missed for two years. |
Part 5: Additional Action Plan in Support of Student Learning (If Appropriate)
Upcoming Year | Changes Planned for the upcoming year | Data Motivating this change |
---|---|---|
2022-2023 | The Pathstream contract has ended and we are revaming the Project Managememt suite of courses. | BUSA 1198: 64% of students met the goal of having 71% of students achieve 71% or higher on their final project
BUSA 2198: 69% of students met the goal of having 71% of students achieve 71% or higher on their final project
These classes (and projects) have been taught using the Pathstream LMS which has resulted in targets being missed for two years.
|
2022-2023 | ||
2022-2023 |